July 30th, 2022

Construction work continues rapidly over on the site of Project Amazon. Steelwork for the coasters station building and the maintenance shed is now mostly completed. It is expected that some staircases are to be installed in the coaster’s station. Internal walls are set to be installed within the maintenance shed Read more…

July 6th, 2022

Merely a couple of days after our last update, we’re back! The station framework has flown up rapidly. It seems that the majority of the steelwork is now up. With details such as the floor, stairways and walls yet to be put into place. We can now see how wide Read more…

July 4th, 2022

With things progressing well across most of the site now, it’s time for another update. This time, something new has started to rise! With the steelwork now thought to be completed on the main theming feature, crews have started up work elsewhere. The station building is their next target, with Read more…

June 23, 2022

The mountain rises! In our latest update, we can see the steelwork for what is suspected to be a Jaguar-shaped mountain rising up. The framework also includes an internal network of access steps and levels. Could this be for a fire, water or mist effect? The mountain forms the centrepiece Read more…

June 7, 2022

Once again it is time for another exclusive update. Today, however, big changes are being made on-site at Chessington. Theming Goes Vertical That’s right. The huge animal-themed mountain feature has started to go vertical. With structural steelwork rising. The steelwork is built on some of the earlier poured foundations and Read more…

May 26, 2022

Here we go again with another exclusive Chessington Buzz update! Work is progressing well on the rebar grid which will form the foundations of the ride station. With the layout of the building now taking shape, we can also see that structural steel has been delivered. Stored in the car Read more…

May 7, 2022

Footers are going in! That’s right. In this exciting update, we can exclusively show that footers for Chessington’s new roller coaster are starting to take shape. The footer bolts have been installed within the precast concrete tubes. These tubes form the surround of the footer, with the bolts installed on Read more…

April 23, 2022

Here we go again! Update time! Things are progressing really well now. A large rebar cage has been installed alongside one of the park’s car parking roads. This new rebar cage is thought to be one of the ride’s first footers. This has also seen the relocation of one of Read more…

April 14, 2022

We’re back at Chessington again, which means only one thing! Amazon Update time! More progress is being made on-site rapidly every visit! This time we’ve got some solid foundations in place! Throughout the area, piling continues. The rebar poles go into the piles and are made up ready to be Read more…

April 4, 2022

We promised frequent updates, so here we go with another Project Amazon update! Piling has begun at Chessington. The piling rig has started to put large concrete piles into the ground in preparation for ride footers. The piles are dug many meters into the ground and have the footers and Read more…