Updates

Uncategorised

August 9th, 2022

With every update we post, so much more happens on site. Things are still progressing well and the changes are evident to see. Towards the bottom of the site, the Read more…

By Admin, 5 daysAugust 2022 ago
Construction

July 30th, 2022

Construction work continues rapidly over on the site of Project Amazon. Steelwork for the coasters station building and the maintenance shed is now mostly completed. It is expected that some Read more…

By Admin, 2 weeksJuly 2022 ago
Construction

July 6th, 2022

Merely a couple of days after our last update, we’re back! The station framework has flown up rapidly. It seems that the majority of the steelwork is now up. With Read more…

By Admin, 1 monthJuly 2022 ago
Construction

July 4th, 2022

With things progressing well across most of the site now, it’s time for another update. This time, something new has started to rise! With the steelwork now thought to be Read more…

By Admin, 1 monthJuly 2022 ago
Construction

June 23, 2022

The mountain rises! In our latest update, we can see the steelwork for what is suspected to be a Jaguar-shaped mountain rising up. The framework also includes an internal network Read more…

By Admin, 2 monthsJune 2022 ago
Construction

June 7, 2022

Once again it is time for another exclusive update. Today, however, big changes are being made on-site at Chessington. Theming Goes Vertical That’s right. The huge animal-themed mountain feature has Read more…

By Admin, 2 monthsJune 2022 ago
Construction

May 26, 2022

Here we go again with another exclusive Chessington Buzz update! Work is progressing well on the rebar grid which will form the foundations of the ride station. With the layout Read more…

By Admin, 3 monthsMay 2022 ago
Construction

May 7, 2022

Footers are going in! That’s right. In this exciting update, we can exclusively show that footers for Chessington’s new roller coaster are starting to take shape. The footer bolts have Read more…

By Admin, 3 monthsMay 2022 ago
Construction

April 23, 2022

Here we go again! Update time! Things are progressing really well now. A large rebar cage has been installed alongside one of the park’s car parking roads. This new rebar Read more…

By Admin, 4 monthsApril 2022 ago
Construction

April 14, 2022

We’re back at Chessington again, which means only one thing! Amazon Update time! More progress is being made on-site rapidly every visit! This time we’ve got some solid foundations in Read more…

By Admin, 4 monthsApril 2022 ago

Posts navigation

1 2 3 Next
Recent Posts
  • August 9th, 2022
  • July 30th, 2022
  • July 6th, 2022
  • July 4th, 2022
  • June 23, 2022
Archives
  • August 2022
  • July 2022
  • June 2022
  • May 2022
  • April 2022
  • March 2022
  • February 2022
  • January 2022
  • October 2021
  • August 2021
  • May 2021
Categories
  • Construction
  • Consultation
  • In Depth
  • Planning
  • Uncategorised
  • Home
  • Consultation
  • Planning
  • Updates
Hestia | Developed by ThemeIsle