September 8th, 2022

Today, we have a fantastic update. Coaster supports have arrived at Chessington World of Adventures. The supports, painted brown in colour form the backbone of the new roller coaster. Bolted to the foundations that wrap around the site, the green steel track will then sit connected to the ground via Read more…

September 6th, 2022

Construction continues over on the World of Jumanji! The Jaguar Shrine continues to rise and receive its outer details. The team at Koda Creative are continuing their detail work and the figure is starting to really take shape. Once the initial coating is completed, more layers of concrete go on Read more…

August 9th, 2022

With every update we post, so much more happens on site. Things are still progressing well and the changes are evident to see. Towards the bottom of the site, the maintenance building now has most of its walls connected. The roof is in place and it seems likely that work Read more…

July 30th, 2022

Construction work continues rapidly over on the site of Project Amazon. Steelwork for the coasters station building and the maintenance shed is now mostly completed. It is expected that some staircases are to be installed in the coaster’s station. Internal walls are set to be installed within the maintenance shed Read more…

July 6th, 2022

Merely a couple of days after our last update, we’re back! The station framework has flown up rapidly. It seems that the majority of the steelwork is now up. With details such as the floor, stairways and walls yet to be put into place. We can now see how wide Read more…

July 4th, 2022

With things progressing well across most of the site now, it’s time for another update. This time, something new has started to rise! With the steelwork now thought to be completed on the main theming feature, crews have started up work elsewhere. The station building is their next target, with Read more…

June 23, 2022

The mountain rises! In our latest update, we can see the steelwork for what is suspected to be a Jaguar-shaped mountain rising up. The framework also includes an internal network of access steps and levels. Could this be for a fire, water or mist effect? The mountain forms the centrepiece Read more…

June 7, 2022

Once again it is time for another exclusive update. Today, however, big changes are being made on-site at Chessington. Theming Goes Vertical That’s right. The huge animal-themed mountain feature has started to go vertical. With structural steelwork rising. The steelwork is built on some of the earlier poured foundations and Read more…

May 26, 2022

Here we go again with another exclusive Chessington Buzz update! Work is progressing well on the rebar grid which will form the foundations of the ride station. With the layout of the building now taking shape, we can also see that structural steel has been delivered. Stored in the car Read more…

May 7, 2022

Footers are going in! That’s right. In this exciting update, we can exclusively show that footers for Chessington’s new roller coaster are starting to take shape. The footer bolts have been installed within the precast concrete tubes. These tubes form the surround of the footer, with the bolts installed on Read more…